This is the page for the third year of the house project. Neither the house nor this page are done yet. I started the year with no anticipation that I'd complete the house this year or that I'd ever get the money I have invested in it back for use in my own life. I had hoped at the start (in May) that my brother-in-law would finish getting the construction loan he had started applying for the previous Fall and pay me back the money I have spent on the project (buying services and building materials). I had planned use that money to hire someone to work with me on the projcet. This would be beneficial to me as I'm losing more money from the time spent not working for pay than I'd lose paying someone to help the work go faster. For reasons known to him, the loan didn't happen. I believe he's paid for a lot of incidental materials and services and two floor pours with credit cards for which he has negotiated a sufficiently low interest and repayment rate as to find it acceptable.

What we've gotten done this past year is the floor poured over the top of the basement (They said it's the first structural elevated slab in Cortland since the prison was built.), the floor poured in the garage, most of the backfilling around the basement, and most of the form construction for the first floor walls. While I was working in Sitka Alaska in the Spring of 2008 I purchased a small camera that is able to save its photos as raw files. My old laptop runs the software capable of editing raw files with pathetic slowness, so I put off working on the photos until the time I anticipated spending at my parents' place in WV over the holidays. Then the economy crashed, and when Bob Walton of Maritime Recruiters called me with a job offer in mid-December, I felt that I'd better accept it as another might not come along soon. I plan to finish this page when I get back to my parents' place where the photos are stored and I have some time to work on them.

As a result of not earning money for more than half of the year for three years and not anticipating an end to the house project anytime soon, I anticipate taking 2009 off from the house project and earning enough to at least repay my parents the money I've borrowed from them to keep up with my own bills during the latter half of the last three years.

Here's photos - words to follow


Arrival - May 19th, 2008

The way the project looked when I arrived on May 19th of 2008. Baby Robins May 23rd, 2008 Baby Robins May 24th, 2008 Baby Robins May 24th, 2008

Ground Floor Prep

Preparing for the First Floor Pour - June 2nd, 2008 Preparing for the First Floor Pour - June 15th, 2008 Preparing for the First Floor Pour - June 20th, 2008 Preparing for the First Floor Pour - June 22nd, 2008 Preparing for the First Floor Pour - June 25th, 2008 Preparing for the First Floor Pour - June 29th, 2008 Preparing for the First Floor Pour - June 30th, 2008 Preparing for the First Floor Pour - July 12th, 2008

Bracing underneath for the First Floor Pour - July 27th, 2008 Bracing underneath for the First Floor Pour - July 27th, 2008 Bracing underneath for the First Floor Pour - July 27th, 2008 Bracing underneath for the First Floor Pour - July 27th, 2008 Bracing underneath for the First Floor Pour - July 27th, 2008 Bracing underneath for the First Floor Pour - July 27th, 2008

A few close - ups

Some plastic leaves and some basement lighting supports in the guest room floor Part of the floor under the bathroom near the Garage Part of the floor under the bathroom near the Garage Part of the floor under the bathroom in the Guest Room

The Ground Floor Pour - July 25th, 2008

First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008
First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008
First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008
First Floor Pour - July 25th, 2008 First Floor Pour - July 25th, 2008 First Floor Pour - July 30th, 2008 First Floor Pour - August 4th, 2008

Garage Floor Prep


Preparation for the Garage Floor Pour August 2nd, 2008 Preparation for the Garage Floor Pour August 4th, 2008 Preparation for the Garage Floor Pour August 7th, 2008 Preparation for the Garage Floor Pour August 10th, 2008 Preparation for the Garage Floor Pour August 11th, 2008 Preparation for the Garage Floor Pour August 11th, 2008 Preparation for the Garage Floor Pour August 10th, 2008 Preparation for the Garage Floor Pour August 11th, 2008 Preparation for the Garage Floor Pour August 12th, 2008

The Garage Floor Pour - August 12, 2008


The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008
The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008 The Garage Floor Pour August 12th, 2008

Generator Exhaust Project - August 14th, 2008


Generator Exhaust Project - August 14th, 2008 Generator Exhaust Project - August 14th, 2008 Generator Exhaust Project - August 14th, 2008

Backfilling - August 16th, 2008


Backfilling - August 16th, 2008 Backfilling - August 16th, 2008

Basement Ceiling - August 15th, 30th, 2008


The Basement Ceiling - August 15th, 2008 The Basement Ceiling - August 30th, 2008

First Floor Use - August 21st, 27th, 2008


Chairs on the Ground Floor after curing - August 21st, 2008 Cars on the Garage Floor after curing - August 27th, 2008

The Basement Stairs September 7th - 9th, 2008


The Basement Stairs - September 7th, 2008 The Basement Stairs - September 7th, 2008 The Basement Stairs - September 7th, 2008 The Basement Stairs - September 9th, 2008

Ground Floor Walls - September 21st - November 16th, 2008


The Big Sawzall Blade - September 5th, 2008 The Ground Floor Walls - September 21st, 2008 The Ground Floor Walls - September 22nd, 2008 The Ground Floor Walls - September 25th, 2008 The Ground Floor Walls - October 5th, 2008 The Ground Floor Walls - October 5th, 2008 The Ground Floor Walls - October 18th, 2008 The Ground Floor Walls - October 18th, 2008 The Ground Floor Walls - October 18th, 2008
The Ground Floor Walls - November 5th, 2008 The Ground Floor Walls - November 5th, 2008 The Ground Floor Walls - November 7th, 2008 The Ground Floor Walls - November 7th, 2008 The Ground Floor Walls - November 16th, 2008 The Ground Floor Walls - November 16th, 2008 The Ground Floor Walls - November 16th, 2008 The Ground Floor Walls - November 16th, 2008

On to Part (year) Four.


Here's a link back.